Saint Mary Road Port Project

10/20/2017

The contract for Saint Mary Road Port Project was signed on October 12, 2013. Commenced on November 21, 2012, it is invested by BADEA, OFID and the Government of Madagascar.

Bata Port Project in Equatorial Guinea

03/15/2017

The construction of Bata Port Project started in early February, 2009, and the construction period is 65 months. So far, Bata Port has been all completed; all the unit projects under the contract have been accepted.

The Counter-Silting Dike Construction & Dredging Project in the Friendship Harbor of Mauritania

11/19/2015

The 585.1m-long Friendship Harbor, located at the Nouakchott Atlantic frontage, has been playing the role of the communicative hub of trade transportation in West Africa and it has greatly enhance the economic development of Mauritania and the neighboring countries since the completion of the first phase of the project.

OYO Inland Wharf Project in Congo-Brazzaville

11/19/2015

OYO Inland Wharf Project consists of passenger terminal, freight terminal, storage space and harbor road, house building, pipe network and electric power project etc.. The area covers about 90900 m2, and the wharf face-line is in a straight line whose total length is 494m. The construction formally started on August 21, 2013, and the construction period is 36 months.

No. 19 Berth in Mombasa

11/19/2015

Commenced on March 1, 2011 and with the construction duration of 24 months, it is the first port project of Kenya since 1984, and is also CCCC’s first port project in Kenya.

Port
  •   10/20/2017

    Saint Mary Road Port Project

    The contract for Saint Mary Road Port Project was signed on October 12, 2013. Commenced on November 21, 2012, it is invested by BADEA, OFID and the Government of Madagascar.

  •   03/15/2017

    Bata Port Project in Equatorial Guinea

    The construction of Bata Port Project started in early February, 2009, and the construction period is 65 months. So far, Bata Port has been all completed; all the unit projects under the contract have been accepted.

  •   11/19/2015

    The Counter-Silting Dike Construction & Dredging Project in the Friendship Harbor of Mauritania

    The 585.1m-long Friendship Harbor, located at the Nouakchott Atlantic frontage, has been playing the role of the communicative hub of trade transportation in West Africa and it has greatly enhance the economic development of Mauritania and the neighboring countries since the completion of the first phase of the project.

  •   11/19/2015

    OYO Inland Wharf Project in Congo-Brazzaville

    OYO Inland Wharf Project consists of passenger terminal, freight terminal, storage space and harbor road, house building, pipe network and electric power project etc.. The area covers about 90900 m2, and the wharf face-line is in a straight line whose total length is 494m. The construction formally started on August 21, 2013, and the construction period is 36 months.

  •   11/19/2015

    No. 19 Berth in Mombasa

    Commenced on March 1, 2011 and with the construction duration of 24 months, it is the first port project of Kenya since 1984, and is also CCCC’s first port project in Kenya.